The Jobs for Veterans’ State Grants (JVSG) are mandatory, formula-based staffing grants to (including DC, PR, VI and Guam). The JVSG is funded annually in accordance with a funding formula defined in the statute (38 U.S.C. 4102A (c) (2) (B) and regulation and operates on a fiscal year (not program year) basis, however, performance metrics are collected and reported (VETS-200 Series Reports) quarterly (using four “rolling quarters”) on a Program Year basis (as with the ETA- 9002 Series). Currently, VETS JVSG operates on a five-year (FY 2015-2019), multi-year grant approval cycle modified and funded annually.
In accordance with 38 U.S.C. § 4102A(b)(5) and § 4102A(c), the Assistant Secretary for Veterans' Employment and Training (ASVET) makes grant funds available for use in each State to support Disabled Veterans' Outreach Program (DVOP) specialists and Local Veterans' Employment Representatives (LVER) staff. As a condition to receive funding, 38 U.S.C. § 4102A(c)(2) requires States to submit an application for a grant that contains a State Plan narrative, which includes:
- a. Contents of a Complete Ui Sqsp Package
A complete UI SQSP package includes the following documents, as described in Chapter 1, ETA Handbook 336, 18th Edition:
- a. Contents of a Complete Ui Sqsp Package
a. 3. The State Plan Narrative
The State Plan Narrative is a vital element of the SQSP that provides a vehicle for sharing with the Federal partner State-specific efforts that affect the administration of the UI Program. The State Plan Narrative allows the State to describe in a single narrative: a) State performance in comparison to the Government Performance Review Act goals; b) actions planned to correct deficiencies regarding UI programs, UI program reviews and reporting requirements; and c) results of customer satisfaction surveys (optional).
Current Narrative:
STATE PLAN NARRATIVE
(Washington - Federal Fiscal Year 2018 Update)
Overview
Washington’s priorities for the FY 2017-18 SQSP continue to focus on the timely and accurate payment of UI benefits and integrity efforts.
Washington’s major change during FFY 2017 was the implementation of our new UI benefits system, which went live on January 3, 2017. This change was very positive for staff and customers alike, but as expected, created significant upheaval in our operations and business processes. We are working to stabilize and correct outstanding issues to ensure customers are minimally impacted by these changes. Washington has and will continue to collect feedback from customers and staff to ensure the various process improvements for the UI Benefits system are remedied in a timely manner.
Washington ESD has had a number of staff changes in key roles, including leadership in UI operations and policy as well as our IT division. These changes, while positive, have impacted our plans and timelines. We continue to recruit and hire qualified staff to fill key positions, and anticipate increasing our training efforts for ongoing process improvements. We also continue to utilize Lean methodology to apply resources where needed and improve processes and outcomes.
Washington continues to work with workforce system partners, employment service and program staff to meet WIOA program requirements.
Federal Emphasis (GPRA Goals)
Washington met two of three GPRA goals for FFY 2017. First Payment Promptness fell slightly below standard, which we attribute mostly to the implementation of our new UI benefits computer system and the associated business process changes. We continue to work to stabilize and improve the system as well as the human interactions with it to meet this goal.
Washington will continue to strive to meet GPRA goals and provide adequate administrative support to achieve goals and targets.
Program Review Deficiencies
Washington did not have any program deficiencies during the reporting period. We will continue to conduct reviews as required.
D. Program Deficiencies
Additions for 2018:
Lower Authority Appeals Time Lapse (30 days): ALP ≥60%, Washington 49.84%
With the launch of our new UI Benefits system in January 2017, claimants were given substantially greater access to file appeals independent of agents via our e-services interface. This led to a significant increase in the number of appeals filed, and placed great demand on existing staff at the claims centers and the Office of Administrative Hearings (OAH). Additionally, the new system required different processes and workflows to assemble appeals packages for submittal to OAH.
We are beginning by reviewing the data to see specifically where the increase in appeals is impacting operations - whether it be an increase in specific types of appeals, system and workflow issues regarding appeal filing, the sheer volume of appeals filed, or the lack of agent involvement in the filing that may have resolved issues without the formal filing of an appeal. Once the root causes are more clearly identified, we will develop a plan to improve performance that specifically addresses the needs.
Lower Authority Appeals Time Lapse has not historically been a problem for Washington. We expect much of the shortfall to be due to technology and workflow changes associated with the new UI Benefits system. We will continue to monitor performance at least monthly and direct resources as appropriate.
Improper Payments Measure: ALP 10%, Washington 13.77%
Washington has historically had a good balance between prompt payment of UI benefits and strong efforts to identify and recoup benefits that may have paid erroneously. Washington has been a leader in work-search requirements and other strong measures that have been adopted nationally to improve the administration of UI benefits.
The time period measured for the Improper Payments Measure (June 28, 2015 to June 25, 2016) was uniquely turbulent in the administration of UI in Washington. Our UI tax system had been launched and was stabilizing; and our UI benefits system was in development with a significant number of business area staff lending their expertise to the project. The vacancies left in the operational areas by the business staff deployed to the project meant existing staff were stretching to cover the work, and new staff were learning the program. At the same time, our BAM program was struggling to fix long-standing staffing shortages and sampling deficiencies. All these factors combined to add confusion to the root causes of our improper payment measure for that time period. Since the time period measured, we have made progress on the UI Tax system stabilization; implemented our new UI Benefits system, reorganized our operational and technology branches under new leadership and new structures, and significantly changed the way we approach our daily work.
It is our first priority to develop ways to track in real-time our improper payments, such that we’re not dependent on lagging measurements. This includes robust data available in our new system, as well as significantly improved efforts to communicate errors found in BAM reviews back to operations staff. At the same time, we continue to review our efforts to reduce improper payments; work with the new UI systems to ensure faster detection and stopping of invalid claims; and assisting our customers to understand their rights and responsibilities as beneficiaries of UI payments.
Reporting Deficiencies
As noted in our recent TPS Review Report, Washington continues to struggle with data especially in regard to our Next Generation Tax System (NGTS). Our response to the TPS Review’s findings will include a plan for corrective actions to address these deficiencies.
Customer Service Surveys
Nothing to report at this time.
Other (e.g., approach to maintaining solvency, requests for technical assistance)
We appreciate our partnership with regional office staff, and their willingness to provide formal and informal technical assistance on a variety of issues. We intend to continue to use their expertise as we move forward to improve our operations.
H. Assurances
Washington notes that strictly speaking, we are out of compliance with the requirements to annually review both the Contingency Plan and the System Security Plan. The Biennial State Plan indicated that the last review was “July/August 2016” and “August 2016,” respectively. In the last year we have had significant staff turnover in key roles, but have recently filled roles relevant to this effort including Chief Technical Officer and Chief Information Security Officer. With these roles filled, the reviews have been scheduled as stated below. We will provide confirmation to the regional office when the reviews are complete.
The State will comply with the following assurances:
Assurance of Equal Opportunity (EO).
Assurance of Administrative Requirements and Allowable Cost Standards.
Assurance of Management Systems, Reporting, and Recordkeeping.
Assurance of Program Quality.
Assurance on Use of Unobligated Funds.
Assurance of Prohibition of Lobbying Costs (29 CFR Part 93).
Drug-Free Workplace (29 CFR Part 98).
Assurance of Contingency Planning.
Provide the most recent dates for the following:
Information Technology (IT) Contingency Plan
Implemented: July 2013
IT Contingency Plan Reviewed/Updated: January 2017
IT Contingency Plan Tested: November 2017 (expected)
Assurance of Conformity and Compliance.
Assurance of Automated Information Systems Security.
Provide the most recent dates for the following:
Risk Assessment Conducted: December 2015
System Security Plan Reviewed/Updated: September 2017 (expected)
Assurance of Confidentiality.