2 Year Modification

Plan: Rhode Island PYs 2018-2019
Combined Plan C

Section: Unemployment Insurance Program

Narrative: a. 4.

Published
Located in:
  • Unemployment Insurance (UI)

    The Jobs for Veterans’ State Grants (JVSG) are mandatory, formula-based staffing grants to (including DC, PR, VI and Guam). The JVSG is funded annually in accordance with a funding formula defined in the statute (38 U.S.C. 4102A (c) (2) (B) and regulation and operates on a fiscal year (not program year) basis, however, performance metrics are collected and reported (VETS-200 Series Reports) quarterly (using four “rolling quarters”) on a Program Year basis (as with the ETA- 9002 Series). Currently, VETS JVSG operates on a five-year (FY 2015-2019), multi-year grant approval cycle modified and funded annually.

    In accordance with 38 U.S.C. § 4102A(b)(5) and § 4102A(c), the Assistant Secretary for Veterans' Employment and Training (ASVET) makes grant funds available for use in each State to support Disabled Veterans' Outreach Program (DVOP) specialists and Local Veterans' Employment Representatives (LVER) staff. As a condition to receive funding, 38 U.S.C. § 4102A(c)(2) requires States to submit an application for a grant that contains a State Plan narrative, which includes:

a. 4. Corrective Action Plans (caps)

Corrective Action Plans (CAPs): CAPs are expected as a part of the SQSP when State’s annual performance does not meet the established criteria for core measures, Secretary’s Standards, UI program, assurances, and other program deficiencies identified in the annual SQSP guidance provided by the Department. The CAP must list both specific milestones for key corrective actions or improvement activities, and the completion date for each milestone.

Current Narrative:

Nonmonetary Determination Quality:

A. The Reason for the deficiency.
After reviewing our BTQ cases that failed the review, the majority of cases failed due to the adjudicator not having enough information in the claimant or employer statements as well as not asking the right questions to render a proper decision. The information obtained was just not sufficient to come to a supportable conclusion at the end of the investigation.
B. Provide a description of your "Plan-Do-Check-Act" corrective action plan which will be undertaken to achieve the acceptable level of performance. Examples of major actions and activities; aka, Milestones, include IT requirements, business process analysis, training, implementing process improvements, measuring effectiveness, etc. Please include a description of these actions/activities in each stage of your "Plan-Do-Check-Act" corrective action plan.
Our plan to improve our BTQ scores will begin with the BAM Unit reviewing 5 additional cases each week and scoring them using the BTQ criteria. The BAM Manager and CAU Managers will then meet with the adjudication staff as a group on a monthly basis to discuss the quality of the extra cases being evaluated. This will help us be pro-active with our evaluation of our current case load.
The CAU managers will review 3 cases (1 termination issue, 1 quit issue and 1 non-sep issue) for 2 adjudicators, each week. Each case will be evaluated by the CAU Management team based on the information obtained (using our CAU guide questions as the standard), the written determination based on the facts of the case along with the supporting documentation and the overall effectiveness of the interview. The managers will listen to each of the actual phone calls to determine the quality of the interview and evaluate the written statement relating to each call. Each case will then be evaluated and scored by the managers. Each selected adjudicator will meet individually with the managers to listen to the calls and evaluate the cases. We believe this part of our plan will be effective in holding the adjudicators accountable for their work and elevate their decision making process.
All of our additional case evaluations will be discussed with the individual adjudicators and each evaluation will be tracked on a spreadsheet, showing the progress that is being made by each adjudicator. Following each BTQ quarterly review, the CAU managers in conjunction with the BAM manager will identify:
1) if the BTQ failures were limited to a small of number of adjudicators making the same mistakes. This will result in a one on one meeting with the adjudicator(s) to discuss policy.
2) If the BTQ failures involved multiple adjudicators making the same mistakes. This will result in a training session for the entire adjudication staff.
3) If the BTQ failures are widespread among the adjudication staff regarding a similar issue, this will result in management confirming, in writing, the policy that is confusing the staff. The policy will then be clearly communicated to the staff.
C. If a plan was in place the previous year, an explanation of why the actions contained in that plan were not successful in improving performance; and, an explanation of why the actions now specified will be more successful.
D. A brief description of plans for monitoring and assessing accomplishment of planned actions and for controlling quality after achieving performance goals.
Continued meetings with BAM management and review of cases that pass or fail.
Improper Payments Measures: A. The Reason for the deficiency.
Rhode Island has experienced incremental increases in Improper Payments due to work search requirements. Based on cause analysis, work search continues to negatively impact our improper payment rate because of restrictive language in our Rules and Regulations. The previous language required work search contacts to be verifiable. In many cases, a work search contact cannot be verified due an employer's applicant purge practices, or small business' lack of ability to store applications, etc. Also, some employers cannot be reached for verification after exhaustive attempts. In cases where the contact cannot be absolutely verified due to the aforementioned reasons, investigators will now have the latitude to determine based on the available information whether it can be reasonably assumed the claimant did make work search contact.
B. Provide a description of your "Plan-Do-Check-Act" corrective action plan which will be undertaken to achieve the acceptable level of performance. Examples of major actions and activities; aka, Milestones, include IT requirements, business process analysis, training, implementing process improvements, measuring effectiveness, etc. Please include a description of these actions/activities in each stage of your "Plan-Do-Check-Act" corrective action plan.
Plan: UI submitted changes to the UI/TDI Rules and Regulations in 2016 which would no longer require work search contacts to be verifiable. Those updates to the Rules and Regulations became effective as of August 7, 2018. This will afford staff some latitude in determining whether or not a contact for employment meets Rhode Island's standard for qualifying for a payment. Training has been provided to BAM investigators on the proper and consistent application of the work search requirements within the BAM process. The Administrative Office is confident staff are now applying the rule consistently and properly in all cases. Continued review and training will be provided based on monitoring and data analysis. Finally, Rhode Island will request Technical Assistance from the Regional Office of US DOL if no improvement is shown following the third quarter 2018.
Do: In interviewing the employer and the claimant, BAM investigators will determine the validity of the contacts, and will investigate all three submitted for the key week, etc. We have strengthened our messaging to customers on the work search requirements by requiring staff to advise every caller of UI’s work search policy.
Check: Each case submitted is reviewed by the BAM supervisor. Every work search determination will be reviewed and verified as having met or not met the work search policy and rule. We will regularly monitor our Improper Payment rates to assess the need to implement further changes.
Act: The impact of claimant messaging around the work search requirements will be discussed in weekly meetings with the Administrator overseeing BAM. If adjustments are required to any of these processes, those will be developed on an as-needed basis.
C. If a plan was in place the previous year, an explanation of why the actions contained in that plan were not successful in improving performance; and, an explanation of why the actions now specified will be more successful.
Due to delays in approval of our rule changes regarding work search requirements, Rhode Island was unable to improve work search improper payments. UI Administration is confident that the approval of our more realistic rule and continued monitoring and training will prove to significantly improve our improper payment rate in a short period of time.
D. A brief description of plans for monitoring and assessing accomplishment of planned actions and for controlling quality after achieving performance goals.
The impact of claimant messaging and application of rule changes around the work search requirements will be discussed in weekly meetings with the Administrator overseeing BAM. In addition, staff training will be provided on an as-needed basis based on review of BAM cases to ensure accurate and consistent coding. If adjustments are required to any of these processes, those will be developed on an as-needed basis. We will regularly monitor our Improper Payment rates to assess the need to implement further changes.
Benefits Data Validtion: A. The Reason for the deficiency.
RI was required to validate populations 3, 3a, 4, 5, 12, 13, and 14 in FY 2018. Initially there were problems running the extracts. We requested that the extract files for the seven populations be run at the end of March for the fourth quarter 2017. The programmer did not have permission to access the Sun Server and on two occasions created the extracts for incorrect quarters. In addition, the lead validator had a family emergency resulting in several days of loss work. These issues delayed the start of the validation until the mid of May leaving just four weeks to validate all seven populations. Since population 12 was the only population to pass the report element portion of the validation, the decision was made to validate just populations 4 and 12 since the remaining populations would need to be validated in the next fiscal year.
B. Provide a description of your "Plan-Do-Check-Act" corrective action plan which will be undertaken to achieve the acceptable level of performance. Examples of major actions and activities; aka, Milestones, include IT requirements, business process analysis, training, implementing process improvements, measuring effectiveness, etc. Please include a description of these actions/activities in each stage of your "Plan-Do-Check-Act" corrective action plan.
Our corrective action plan is to begin the validation process earlier.
C. If a plan was in place the previous year, an explanation of why the actions contained in that plan were not successful in improving performance; and, an explanation of why the actions now specified will be more successful.
D. A brief description of plans for monitoring and assessing accomplishment of planned actions and for controlling quality after achieving performance goals.
Populations 3, 3a and 4 will be validated during the quarter ending 12/31/18
Populations 12, 13 and 14 will be validated during the quarter ending 3/31/19
Population 5 along with Mods 3 and 4 will be validated during quarter ending 6/30/19
Tax Data Validation: A. The Reason for the deficiency.
RI has been working on the consortium project and as a result was unable to run data validation extracts as much as it would have liked due to limited resources. RI has since trained the TPS supervisor in the data validation process so that next year RI will be able to run these extracts on a more frequent basis as a result RI should have less failure and be able to submit passing populations.
RI Failed population 1 because RI had reimbursable accounts that were active that had more than 8 quarters of zero.
RI failed tax population 3 because the file extract was pulling in the wrong dates for successor accounts that had a change in liability date after the fact.
Population 4 for RI is still a work in progress. RI has yet to create an extract file for this population that is working correctly. This population extract is very complicated. RI while working on the consortium project had stopped working on updating the program for population 4 as RI was designing a new program for the consortium.
Population 5 failed because one audit was coded as a change audit in our system in error and when the data validation software ran is was picked up as a no change audit. Do to this one error it caused us to fail population 5.
Module 3 was not submitted and validated in time for the deadline but has been since been submitted and finalized.
Module 4 failed because in 2017 RI had a changeover in staff in the audit entry process. The new staff member was entering the completion date as the date the auditor finalized the audit but did not account for the time it took the supervisor to review and process the audit. When the completion date and process dates overlapped quarters, the audit was never reported on the 581 as the 581 had previously ran. This was corrected on 7/28/17 and going forward it should not be an issue. As a result, the numbers on the 581 were understated for the 4th QTR 2016 through the 3rd QTR of 2017.
B. Provide a description of your "Plan-Do-Check-Act" corrective action plan which will be undertaken to achieve the acceptable level of performance. Examples of major actions and activities; aka, Milestones, include IT requirements, business process analysis, training, implementing process improvements, measuring effectiveness, etc. Please include a description of these actions/activities in each stage of your "Plan-Do-Check-Act" corrective action plan.
RI has been working on the consortium project and as a result was unable to run data validation extracts as much as it would have liked due to limited resources. RI has since trained the TPS supervisor in the data validation process so that next year RI will be able to run these extracts on a more frequent basis as a result RI should have less failure and be able to submit passing populations.
RI failed population 1 because RI had reimbursable accounts that were active that had more than 8 quarters of zero. Reimbursable accounts will be reviewed quarterly to determine if they have more than 8 quarters of zero's and will be terminated if necessary. As a result, RI will pass population 1 the next time the extract file is run through the sun system.
RI failed tax population 3 because the file extract was pulling in the wrong dates for successor accounts that had a change in liability date after the fact. RI will review the extract file and errors that were created as a result of Data Validation to determine what adjustment need to be made to the extract file. Once the adjustments are made RI will rerun the DV extract file through the sun system to verify that the changes made have addressed the issue that caused RI to fail Population 3
Population 4 for RI is still a work in progress. RI has yet to create an extract file for this population that is working correctly. This population extract is very complicated. RI while working on the consortium project had stopped working on updating the program for population 4 as RI was designing a new program for the consortium. Now that new staff has been trained RI will review the Data Validation(DV) requirements and continue to make modifications to the extract file as required per DV requirements for the current RI tax system. RI will also review the current 581 programming for accounts receivable to verify that it to is programmed correctly per 581 requirements. Once both files have been reviewed and changes are addressed if needed RI will rerun the extract file through the sun system. If there are any errors RI will continue to address them until Population 4 passes the 2% Data Validation requirements and sample.
Population 5 failed because one audit was coded as a change audit in our system in error and when the data validation software ran is was picked up as a no change audit. Do to this one error it caused us to fail population 5. A clerical error created population to fail as a result staff will be retrained on entering audits into the RI tax system
Module 3 was not submitted and validated in time for the deadline but has been since been submitted and finalized.
Module 4 failed because in 2017 RI had a changeover in staff in the audit entry process. The new staff member was entering the completion date as the date the auditor finalized the audit but did not account for the time it took the supervisor to review and process the audit. When the completion date and process dates overlapped quarters, the audit was never reported on the 581 as the 581 had previously ran. This was corrected on 7/28/17 and going forward it should not be an issue. As a result, the numbers on the 581 were understated for the 4th QTR 2016 through the 3rd QTR of 2017.
C. If a plan was in place the previous year, an explanation of why the actions contained in that plan were not successful in improving performance; and, an explanation of why the actions now specified will be more successful.
Last year RI had a plan in place for population 4 and was unsuccessful accomplishing this plan. This was directly related to the fact that the RI resources allocated to the Consortium project are the same resources needed for Data Validation from both the business and IT departments. Additional business resources have been trained for Data Validation that are not fully allocated to the consortium project. As a result, RI is more confident that they will have the time to address Population 4.
D. A brief description of plans for monitoring and assessing accomplishment of planned actions and for controlling quality after achieving performance goals.
RI will once a quarter allocate time for data validation to make sure that the milestones below will be met or adjusted if needed on a regular basis.
Benefit Accuracy Measurement (BAM): A. The Reason for the deficiency.
Until May 7, 2018, BAM NDNH crossmatch hits were deleted from the program if they had a previous Benefit Payment Control (BPC) hit. This issue was corrected as of May 7, 2018. We have been assured by IT that duplicate hits are not longer being excluded.
B. Provide a description of your "Plan-Do-Check-Act" corrective action plan which will be undertaken to achieve the acceptable level of performance. Examples of major actions and activities; aka, Milestones, include IT requirements, business process analysis, training, implementing process improvements, measuring effectiveness, etc. Please include a description of these actions/activities in each stage of your "Plan-Do-Check-Act" corrective action plan.
BAM detected an issue in 2017 regarding programming which excluded BAM NDNH "hits" already identified in the PBPC crossmatch. IT was informed of the requirement that BAM receive NDNH hits separately from the BPC process. In May, 2018, IT corrected the program to allow BAM to receive NDNH hits separately, although BPC may have received one previously.
C. If a plan was in place the previous year, an explanation of why the actions contained in that plan were not successful in improving performance; and, an explanation of why the actions now specified will be more successful.
BAM had requested an update to NDNH programming to no longer exclude duplicate hits from the BAM NDNH process in early 2017. Due to IT involvement in consortium, many UI IT requests were pending for significant periods of time. When consortium was placed on hiatus, IT began working on those UI projects that had been pending. BAM requested the NDNH issue be resolved with priority. As such, the work for this project was completed in May, 2018.
D. A brief description of plans for monitoring and assessing accomplishment of planned actions and for controlling quality after achieving performance goals.
Administrative Benefits is monitoring the programming to ensure it is working properly. Although we have not yet seen a BAM NDNH hit, we have informed the BAM unit to advise as soon as the first hit is identified. A follow up request to IT to verify proper programming resulted in a reiteration that the program is operating correctly , and duplicates are no longer excuded from the BAM NDNH program.
Facilitate Reemployment: A. The Reason for the deficiency.
Rhode Island failed the Acceptable Level of Performance in the Facilitation of Reemployment measure by .3% for first payments during the period October 1, 2016 through September 30, 2017. In researching the sources from which we derive our reemployment data, it was discovered that no out-of-state wage data is included in our reemployment reporting for UI claimants. We have requested corrective programming to include WRIS data to identify individuals who return to work in another state. This project is included in a list of IT priorities to complete. We have requested this correction be completed prior to year-end 2018.
B. Provide a description of your "Plan-Do-Check-Act" corrective action plan which will be undertaken to achieve the acceptable level of performance. Examples of major actions and activities; aka, Milestones, include IT requirements, business process analysis, training, implementing process improvements, measuring effectiveness, etc. Please include a description of these actions/activities in each stage of your "Plan-Do-Check-Act" corrective action plan.
Plan: Rhode Island has requested corrective programming to include Interstate reemployment in reporting. We will continue to work closely with our partners in Workforce Development to develop strategies to assist UI customers in becoming reemployed as soon as possible.
Do: UI Administration will work with IT to ensure completion of corrective programming prior to 12/31/2018.
Check: Facilitation of Reemployment measures will be monitored and assessed on a quarterly basis to ensure Rhode is meeting and exceeding acceptable levels of performance.
Act: All issues detected during the monitoring and analysis phase will be addressed with IT and/or WD. In addition, technical assistance will be requested if necessary.
C. If a plan was in place the previous year, an explanation of why the actions contained in that plan were not successful in improving performance; and, an explanation of why the actions now specified will be more successful.
Rhode Island has met or exceeded the acceptable level of performance (ALP) in Facilitation of Reemployment of UI Claimants since the last biennial State Quality Service period. We are confident corrective programming to include Interstate reemployment will allow for improvement to exceed future ALP’s.
D. A brief description of plans for monitoring and assessing accomplishment of planned actions and for controlling quality after achieving performance goals.
Facilitation of Reemployment measures will be monitored and assessed on a quarterly basis to ensure Rhode is meeting and exceeding acceptable levels of performance.